Policy Text:
Existing and future waste disposal sites that do not require approval under the Environmental Protection Act (Certificate of Approval or Environmental Compliance Approval) are designated for the purpose of Section 58 of the Clean Water Act, 2006 requiring a Risk Management Plan in areas where they could be significant drinking water threats. This policy addresses the following threat sub categories:
Waste Disposal Site - PCB Waste Storage;
Waste Disposal Site - Storage Of Hazardous Waste At Disposal Sites;
Waste Disposal Site - Storage of wastes described in clauses (p), (q), (r), (s), (t)
or (u) of the definition of hazardous waste under Ontario Regulation 347/09.
Implementer: Risk Management Official - Municipality
Applicable Area: This policy applies to the following areas:
Waste Disposal Site - PCB Waste Storage, Waste Disposal Site - Storage of wastes described in clauses (p), (q), (r), (s), (t) or (u) of the definition of hazardous waste:
WHPA A and B, and IPZ 1 (vulnerability score of 10) - Madoc, Tweed, Deloro, Peats Point, Point Anne, Picton, and Ameliasburgh.
Waste Disposal Site - Storage Of Hazardous Waste At Disposal Sites:
WHPA A and B, IPZ 1 and 2 (vulnerability score of 9 or greater) - Madoc, Tweed, Deloro, Peats Point, Belleville (IPZ 1), Picton (IPZ 1 and 2), Deseronto (IPZ 1), Ameliasburgh (IPZ 1), Napanee (IPZ 1) and Point Anne (IPZ 1 and WHPA and B).
Tools: Risk Management Plan pursuant to Section 58 of the Clean Water Act, 2006.
Legal Effect: Must Conform (See Appendix C, List H)
Effective Date: When the Plan takes effect for future activities and within 2 years for existing activities.
Monitoring Policy (See Appendix C, List F):
The risk management official shall submit a report by February 1st of each year to the Quinte Source Protection Authority summarizing the mandatory requirements for the previous calendar year, as specified in Section 65 of Ontario Regulation 287/07 under the Clean Water Act, 2006.