Where existing and future onsite sewage systems with a design capacity greater than 10,000 litres per day that have or require a Certificate of Approval/Environmental Compliance Approval under the Ontario Water Resources Act and could be a significant threat, the Ministry of the Environment shall complete the following:
Existing Systems
If Policy 2-1-E & F cannot be met, then the Ministry shall:
1) Review and consider including adequate terms and conditions to address the drinking water threat including an emergency plan in the event of a failure of the system; and
2) Review and consider including requirements for onsite monitoring to ensure that the system is functioning as designed and require the proponent to have the system inspected regularly using a standard equal to or greater than the inspection protocols of the ‘On-Site Sewage Maintenance Inspection’, document dated March 2011 as amended from time to time, developed by the Ministry of Municipal Affairs and Housing.
Future Systems
If Policy 2-1-E & F cannot be met and where municipal studies have shown that an onsite sewage system can be supported by the area (Policy 2-3-F), then the Ministry shall:
1) Consider adequate terms and conditions, including an emergency plan in the event of a failure of the system, to ensure that the system does not become a significant drinking water threat; and
2) Consider terms and conditions to include requirements for onsite monitoring to ensure that the system is functioning as designed and require the proponent to have the system inspected regularly using a standard equal to or greater than the inspection protocols of the ‘On-Site Sewage Maintenance Inspection’, document dated March 2011 as amended from time to time, developed by the Ministry of Municipal Affairs and Housing.
Applicable Areas:
- WHPA A and B (vulnerability score of 10) - Deloro, Madoc, Peats Point, Point Anne and Tweed and
- IPZ 1 (vulnerability score of 10) - Ameliasburgh, Picton and Point Anne.
- Issues Contributing Area - Madoc and Tweed.
Effective Date: When the Plan, or any plan amendment, as applicable, takes effect for future activities and within 3 years for existing activities.