Policy Id:

SPR/SPA:

Risk:

Implementing Body

Legal Effect

Policy Tool

Threat Type

Status

Comment

Policy Text:

The following activities are designated for the purpose of Section 58 'Risk Management Plans' of the Clean Water Act in the Windsor IPZ-2, in those cases in which the activity is not subject to Provincial Instrument: the future application of non agricultural source material (NASM) such that:

- the application of NASM (no volume threshold) that contains material generated by a meat plant or sewage works and the application could result in pathogen(s) in the surface water.

The Risk Management Plan will include the requirements of a NASM plan as per the Nutrient Management Act, for the application of NASM. Therefore the Risk Management Official (RMO) will obtain documentation from the owner of the facility that demonstrates that the requirements of a NASM plan are met. The RMO will ensure that the owner of the facility has the risk management plan prepared by someone certified to develop a NASM plan that meets the requirements of Reg. 267/03.

The Risk Management Official may require additional conditions in the Risk Management Plan, to be met such that water bodies are protected adequately from the application of NASM. The Risk Management Official will have discretion as to what constitutes a satisfactory Risk Management Plan.

The above applies to the future significant threat of the application of Non Agricultural Source Material (NASM), in the vulnerable area:
- Windsor IPZ-2

For future threats, the date of compliance is when the Source Protection Plan takes effect.

For existing threats, the Risk Management Official shall comply with the policy within 5 years from the date the Plan the Plan takes effect.

Monitoring Text:

W2-applNASM-2 (CWA Monitoring Policy): In accordance with Section 81 of the Clean Water Act, the Risk Management Official (RMO) shall prepare and submit a report to the Source Protection Authority which summarizes the actions taken to comply with policy W2-applASM-1 (Clean Water Act).
The above applies to the future significant threat of the application of Non Agricultural Source Material (NASM), in the vulnerable area:
Windsor IPZ-2.